Altamaha Riverkeeper worked with six local, state, and national
citizens groups to appeal state water withdrawal and discharge permits
for the proposed Plant Washington coal plant. The 850 megawatt coal
plant is a project of Power4Georgians, a company organized
by Cobb Electrical Membership Corporation (EMC) and four other EMCs.
The coal plant will be located in the Ogeechee basin at Sandersville, but
the water to run it will be piped from and discharged to the Oconee
River. ARK thanks our attorneys at Greenlaw and Southern Environmental
Law Center and our fellow citizens groups for their extensive efforts
in filing this appeal.
- April 1, 2011
Oconee River Water Quality Unprotected by Georgia Permit for Coal Plant
- January 19, 2011
Judge clarifies Plant Washington ruling
By S. HEATHER DUNCAN | Macon.com
- January 19, 2011
Center puts river on threatened list
By ERIN FRANCE | OnlineAthens
- January 19, 2011
Georgia wetlands on 2011 endangered listThe Oconee River and the area's cypress trees make a warning list.
By Teresa Stepzinski | Florida Times Union
- January 13, 2011
Cobb case prods new push for EMC changes
By Margaret Newkirk | The Atlanta Journal-Constitution
- January 13, 2011
Corruption scandal casts shadow over Georgia coal plant projects
By Sue Sturgis | FacingSouth
- January 7, 2011
Prosecutors: Cobb Energy saga started with broken promise
By Margaret Newkirk | The Atlanta Journal-Constitution
- November 17, 2010
Pollution case wrapping up
By Merritt Melancon | Athens Banner-Herald
- September 18, 2010
Legal Challenge For Georgia Coal Plant
By Josephine Bennett
- September 13, 2010
Environmental groups fight Middle Ga. coal power plant
By RAY HENRY | Telegraph Wire
- Plant Washington air pollution permit appeals begin in Atlanta September 13
- July 26, 2010
Coal plant permits improper
By Margaret Newkirk | Atlanta Journal Consitution
- July 27, 2010
Ruling clamps interbasin flow
By Rob Pavey and Walter Jones | The Augusta Chronicle
- July 26, 2010
Ruling on power plant narrows definition of interbasin transfers
by Rob Pavey and Walter Jones| Rome News-Tribune
- July 26, 2010
Court Rules Plant Washington Water Permits are Invalid
-
May 11, 2010
Coal Plants Face
New Legal Challenges
by Rickey Bevington | GPB News
-
Media
Release
-
ARK Appeals Plant Washington Water Withdrawal and Discharge
Permits
Petition
for Hearing - NPDES (pdf)
Petition
for Hearing - Surface Water (pdf)
-
Plant Washington Update
Thanks to Greenlaw and SELC for submitting comments on
behalf of ARK and other groups on EPD's draft permits. Facts
and Timeline and Permit Comments from Greenlaw's website. >>
PDF
Georgia Tech energy study >>
- November 2009
Coal
Plant Proposed for Washington County - Facts and Timeline
GreenLaw | Green-Law.org
- October 6, October 20, 2009
Hearings
on Plant Washington Permits
- August 26, 2009
Plant Washington
receives draft permits
By S. Heather Duncan | MACON TELEGRAPH
- June 8, 2008
Battle brewing over
proposed power plant in Washington County
By S. Heather Duncan | Posted on Sun, Jun. 08, 2008
- May 20, 2009
4 EMCs pull
out of proposed midstate plant over possibility of future
coal regulations
By S. Heather Duncan
- May 19, 2009
GSE Statewide
Coalition Calls on EMC Members to Speak Out
Press Release
|
|
| Without your donations the Altamaha Riverkeeper could not repond
when citizens report problems. Please make a tax deductible
donation today >>> |
|