Coal Plant Proposed for Washington County - Facts and TimelineUpdate November 2009: Last year, Power4Georgians submitted an
application to Environmental Protection Division (EPD) to build a
coal-fired power plant at a time when citizens in every state across
the
nation are questioning the safety and efficiency of generating electric
energy from burning pulverized coal. In August 2009 EPD released draft
permits for several of the permits that will be required to operate
and
construct the coal-fired power plant in Sandersville. The permits
include a Prevention of Significant Deterioration (PSD) permit, which
will address the air emissions of such pollutants as mercury, nitrogen
oxides, sulfur dioxide and more. The
permit can be found on EPD's website. EPD
also released a draft National Pollutant Discharge Elimination System
(NPDES) permit, a water withdrawal permit, and a groundwater withdrawal
permit which are not available on EPD's website, but can be obtained
by A public hearing was held in at 6 p.m. on Tuesday, October 20 in Sandersville. The hearing was attended by 321 people; 51 spoke against the plant, 14 in favor of it. Working in partnership with SELC, GreenLaw sent detailed comments on the plant's air, water, and solid waste permits to EPD on October 27. These comments can be viewed here: Water Discharge Permit Comments Groundwater Withdrawal Permit Comments Surface Water Withdrawal Permit Comments Add your name to those opposing new coal plants in Georgia. Final permits are expected to be issued in Spring 2010. |